[edit] Introduction
Just-in-time (JIT) is a production and delivery system developed in Japan in the 1960s and 1970s that ensures materials and components are delivered from the manufacturer to the production site at exactly the right moment to enable immediate use in the production process.
The right materials are supplied in the right order, in the right amount at the right time. The deliveries tend to be regular and in small amounts. The process is also known as ‘Just-in-time production’ and the ‘Toyota Production System’. In recent years the term has been used synonymously with lean manufacturing.
JIT can be critical for some manufacturing processes (such as cars) as it greatly simplifies logistics: components are delivered directly to the production floor so manufacturers do not have to store or warehouse them (or else they only require minimal storage), thereby saving space, time and costs – and making for a more efficient process overall.
Known as a ‘pull’ process, the JIT concept was developed in Japan and is used by the Toyota car company which uses ‘Kanban’ (sign) boards for ordering parts: when a part has been used, the Kanban is taken off the packaging and sent back to the preceding process as an order for an additional item. This sign-based scheduling system signals the need to replenish the product and delivery and maintains production at an optimum level.
Drawbacks of the system are that it works best when production numbers are constant. Also, it is vital that every part fits as it is intended to first time round as there are no other parts available at that time. In addition, if a problem or minor disruption occurs in the supply chain, the manufacturer has no stocks to fall back on and could see production halt at short notice.
[edit] Just-in-time in construction
Products and materials constitute a huge part of the construction process and it has been estimated that greater efficiencies in logistics can reduce waste in construction by up to 35%. Many projects can benefit from JIT delivery and, given the often congested nature of construction sites, rewards similar to those seen in manufacturing industry may be possible.
A prime example is ready-mixed concrete: the perishable nature of this material means that having been mixed to the customer’s exact specification, it must be delivered at the right time, in the right quantity (and at the right specification) to allow pouring before setting takes place. Another example is windows or glazed cladding panels, where on-site storage would necessitate extensive inventory facilities and potential risks of product damage.
JIT in construction has also been referred to as ‘lean construction’ – an adaptation of lean production techniques.
[edit] Just in time delivery / logistics
The BIM Overlay to the RIBA Outline Plan of Work, published by the RIBA in 2012 defined just in time (JIT) delivery, or just in time logistics as: '..receiving raw materials,
products and parts in the factory and then on site as they are needed, rather than days or even weeks before. This allows businesses to significantly cut inventory costs by having fewer unnecessary supplies on hand, and means they have far less material to store and handle. Where buffer stocks are considered necessary (e.g. as a result of a risk analysis), they are specified in terms of time periods linked to the assembly plan (e.g. one day of manufacturing).'
[edit] Related articles on Designing Buildings Wiki
- Time of the essence in construction contracts
- Advanced manufacturing.
- Block planning.
- Design for Manufacture and Assembly (DfMA).
- Egan report.
- Green supply chain management.
- Integrated project delivery (IPD).
- Kanban.
- Lean construction.
- Lean construction - a quality perspective.
- Logistics management.
- Off site materials.
- Flying factory.
- Mean lean green.
- Regularly and diligently.
- Site storage.
- Time at large.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.